Jacket Loadout Milestone Completed for BorWin6 Offshore HVDC Platform

Progress on the BorWin6 Project continues with the successful completion of a fabrication yard milestone in Jebel Ali, United Arab Emirates. Mammoet has completed the transport, loadout and mooring of the 5,461-ton offshore jacket foundation, set to support the BorWin6 offshore converter platform BorWin kappa in the German North Sea.